Composite bridge design and pile freeze back time test in cold and high-altitude permafrost region.pdf

Download (743.69 kB)
conference contribution
posted on 2019-06-16, 01:58 authored by Zhihua XiongZhihua Xiong
After sixty years service of Qinghai-Tibet Road, highway joining Golmud and Lhasa was about
to build. The design scheme for bridge constructed in cold and high-altitude environment needed to be
analyzed. Given the complicated geological and ecological conditions plus high seismic-risk, steelconcrete
composite bridge was recommended. An integral concrete-steel composite girder (ICG)
scheme for permafrost region application was proposed, whose highlights mainly included millfabrication,
overall-girder-erection, fast construction, less labour consumed by cast-in-situ. Field test
for pile freeze back in permafrost region was carried out to investigate the solid bond formation time.
Freeze back test was in the backdrop of the construction of Chala Ping Bridge. Pile freeze back field
test could be a practical reference for the small-span bridge construction schedule drafting in
permafrost region.